Kashmir: Mining expands on rivers despite dire warnings, threatening local livelihoods

The Third Pole

By Athar Parvaiz

The Indian government is in the process of auctioning out approximately 200 blocks in Jhelum river and its tributaries for mining of sand and other minerals. This is despite a recent study warning against large-scale mining operation in the Jhelum, and the advice of an environmental committee against haphazard mining in water bodies.

In 2018, the department of Irrigation and Flood Control (IFC) had asked the Central Water and Power Research Station (CWPRS) to do a detailed technical report covering a host of issues. This was also cited by a World Bank supported study for the Jhelum and Tawi Flood Recovery Project.

"The dredging de-silting/sand mining of the main channel of Jhelum from upstream to Asham is not advisable and may cause difficulties for the flood management. Re-sectioning by increasing the waterway width may possibly be taken up at few places only as recommended in the tour report of CWPRS officers," the technical report concluded.

The report, CWPRS said, is based on the morphological analysis, site visits and analysis of unsteady flow conditions using 1-D unsteady mathematical model with the data provided by the state engineers including the hydrographs, their lag time of flood initiation and capacity curve for the various lakes.

The World Bank supported study also noted:

"In addition to the works to be included in the interim scheme, CWPRS also recommended that further consideration be given to:

  • Cessation of dredging of Jhelum River between Sangam and Asham;
  • Dedication of low lying areas on the left bank of the Jhelum River near the start of the Flood Spill Channel to form detention basins of 49km2 and 44km2) €" uncontrolled development in these areas will preclude their utility for flood retention in the future"

Considering the frequent flood threats from Jhelum and its tributaries, the IFC department has a large authority over these water bodies its approval is mandatory for any extraction of resources from them.

Massive auctions

Despite these recommendations, mineral blocks in the Jhelum and its tributaries (which include sand, boulders and gravel) are being auctioned to mineral extracting contractors and companies by Jammu and Kashmir's Geology and Mining department. By 10 February, 2020 sand blocks in Pulwama, Srinagar and Baramullah districts were auctioned against a bidding amount of Rs 720 million (USD 10 million) for five years.

Applications for the auctioning process were invited online (from 21 December, 2019) for the first time this year at a time when internet connectivity in Kashmir was completely blocked from the first week of August 2019 until the third week of January 2020. Since its restoration, only low-speed (2G) internet connectivity is allowed in the region. Internet was shut down across Kashmir following India's decision to fundamentally change the semi-autonomous status of the mountainous state of Jammu and Kashmir on 5 August, 2019 and its subsequent conversion into a Union Territory (which, under the Indian Constitution, has comparatively limited powers).

Interestingly the reports recommending the limitation of mining were largely conducted during the time that the former state of Jammu and Kashmir was under Governor's Rule, meaning that the central government is going against the very recommendations that were prepared under it.

The joint director of Geology and Mining Department in Jammu and Kashmir, Imtiyaz Ahmad Khan, said that his department has received written permission from IFC. However, an official of the IFC alleged that the IFC faces a lot of pressure from the government to grant such approvals.

"We are strongly against this extensive mining in Jhelum and its tributaries, particularly in south Kashmir as it can have huge consequences on flood management in Kashmir. But we are not able to assert our authority before the government," the official said requesting anonymity.

According to the Water Resources Act  of Jammu and Kashmir, "The control of the bed and banks of all water sources, navigation channels, intake channels, city channels and flood spill channels together with all works that affect the hydraulic conditions in the State shall be under the Irrigation and Flood Control Department."

Khan claimed that his department will take environmental and other concerns into consideration when the contractors start the work. "These are the resources required for raising of developmental infrastructure and housing. But we will definitely seek the opinion of experts on this," Khan said.

But a member of Environmental Appraisal Committee of Jammu and Kashmir, which gives environmental clearance to such projects, said on the condition of anonymity, "We had advised the government during a meeting in December last year that no mining should be allowed in Jhelum and other rivers till there is a basin-wise scientific mining plan as to which area should be declared feasible for mining and which areas should be declared as river sanctuaries."

"Any mining has to be done in a way so that it doesn't cause problems in flood management or functionality of water bodies," he added. Recently, he said, some 160 cases of mining from Jammu region had come to the committee for clearance, "but we didn't find even a single case worth clearance." He, however, alleged that the committee faces a lot of pressure to give clearances.

Now that close to 200 blocks are being formally thrown open for mining of minerals in Kashmir, there are apprehensions that large scale mining for sand and other minerals from the Jhelum and its tributaries can lead to severe environmental consequences. Given that the miners will be operating with the permission from the government, it would be hard for environmental activists and media to question them.

The Indian Institute of Technology (ISM), Dhanbad, cites an interesting example of how this works (or does not work) in practice. "Imagine this: a group of reporters are visiting a picturesque creek of a river on the western coast of India and are taking some photos. They are approached within minutes by a menacing gang in a large vehicle who interrogate them on their presence in the area. One of them roars: "who gave you permission to shoot here? We have purchased the entire creek for Rs 28 crore (INR 280 million / approx. 5.1 million USD). We own it now."

Dominated by non-Kashmiri bidders

Another related issue is that the change in Kashmir's legal status now means that non-residents of the territory can now buy property in Kashmir and conduct business based on the region's resources.

[rq]

***

The Third Pole is a multilingual platform dedicated to promoting information and discussion about the Himalayan watershed and the rivers that originate there. This report was originally published on thethirdpole.net and has been reproduced here with permission.

Also See: Shaheen Bagh's resistance must be viewed sans liberals' romanticism, Right's identity politics

Public clocks of Bombay: In documenting the city's timekeepers, musings on the nature of time 

Mahakali: An account of women's lives along the river basin as men migrate in search of work

Read more on long-reads by Firstpost.